Vanport Square
From CollabLandWiki
Vanport Square- Redevelopment
Portland Development Commission
Commission Briefing
Context: King Neighborhood
Phase 1: Marco Block
Phase 2: Garfield Housing
Phase 3: South Block
Project Description
- Renovation of former Marco Machine Works Building
- New construction on NE corner of site
- Total Development: 42,000 sq.ft.
- Commercial condominiums, targeting local, small businesses
- Approximately 12 to 15 businesses
- 69 + parking spaces
Project Benefits
- Model for well designed, high quality sustainable development on NE Martin Luther King Jr. Blvd.
- Catalytic Investment on critical site in NE Portland
- Community wealth creation
- Property ownership and expansion opportunities for local businesses
- Retail opportunities for community
- Creation and retention of 75+ jobs
- Enhanced pedestrian environment/ courtyard.
Development Agreement
- Project cost: $8.7 million
-PDC $6.8 million
-Net New Markets Tax Credit Proceeds $2.4 million
Project Schedule
June 2006- Design Complete
September 2006- Convey Property, begin construction
November 2007- Project completion
Goals Achieved
- Foster entrepreneurship and wealth creation within the community
- Positive Business Environment
-Create an environment that supports existing businesses, increase profitability, create jobs and encourages the development of new complimentary businesses and industries
- This phase is a key component of PDC’s strategy to revitalize NE Martin Luther King Blvd.